By Grayling Thomas Architects · October 2026
Good CIF funding support for 2027 to 2028 helps a school build a bid it owns: independent evidence of need, a bespoke costed options appraisal, a realistic delivery plan and a cost plan that matches the portal form. The Department for Education (DfE) sets the limits. The accounting officer (or, for a sixth-form college or VA school, a member of the senior management team) stays responsible for the application, a technical adviser cannot submit it, and every school that uses an adviser must now evidence how that adviser was procured. Fees must be proportionate. When a school buys Condition Improvement Fund (CIF) support, scope, procurement and independence matter as much as price.
For how the fund works more broadly, see the practice's complete guide to CIF funding for schools. The round's dates and other rule changes are set out in the practice's guide to the CIF key dates, rule changes and what to prepare by the deadline.
Responsibility for a CIF bid when a consultant helps
The school stays responsible, not the consultant. The DfE's CIF information for applicants says a school can use a technical adviser or representative "to help prepare your application, but this isn’t a mandatory requirement." It then draws the line plainly: "Please note that technical advisers cannot apply on your behalf and even where you use a technical adviser, you remain responsible for the application."
That responsibility sits with a named person. "The accounting officer, or in the case of a sixth-form college or VA school, a member of the senior management team is solely responsible for the CIF application." It covers the accuracy of the information and its submission on the portal, "not any consultant or technical adviser you may be using". The accounting officer's checklist asks for confirmation that the application "has been submitted by the accounting officer/senior management team, not the technical adviser." During the round, any responses to the DfE "must come from the applicant and not any technical advisers that you may be working with."
Good support is built around the school for that reason. An adviser can gather evidence, design the solution and cost the options, but the guidance expects the school to check everything uploaded, "including where you have worked with a technical adviser, and be satisfied that it is correct and nothing is missing before submitting your application." A consultant who hands over a finished pack in the last week leaves the accounting officer signing something they have not had time to understand.
What must a school show about how it appointed its CIF adviser?
A school must show, with records, that it appointed its adviser through a compliant procurement process. This requirement is new this round, and the DfE lists it first under "New requirements for CIF 2027-28": "Applicants must clearly explain and adequately evidence a compliant procurement process undertaken to appoint their technical adviser." The accounting officer's checklist asks for evidence that an adviser was procured "in line with the Academy Trust Handbook, the trust's procurement policy and DfE requirements."
In practice the application has to set out the procurement and selection process, with the evaluation and scoring method used. It has to give the rationale for the appointment and explain how value for money was achieved, including any benchmarking or market testing. It should say how the adviser was selected and, where it applies, which suppliers were considered or invited to bid. Behind all of this the school needs records the DfE can check, such as tender documents, quotations, framework call-off documents, evaluation and approval records and the contract award.
Three details are easy to miss. The rules apply "regardless of how the adviser is remunerated, including where services are provided on a no-win-no-fee basis." The appointment "must cover all stages of the project, including support during application development and, if successful, project delivery", so the procurement should be sized on the value of the services if the bid succeeds. The school must also be able to show "the technical adviser was formally appointed before undertaking work in connection with the project."
The DfE also says it would "strongly recommend appointing advisers who are members of recognised professional bodies, such as the Royal Institution of Chartered Surveyors (RICS), Chartered Institute of Builders (CIOB) or Royal Institute of British Architects (RIBA)." Getting this wrong puts the bid at risk, because failure to evidence a compliant process "may result in the application being disqualified." Once the procurement route is set, judging the adviser's record is a separate question, covered in the practice's guide to choosing a CIF consultant as a standalone academy or small MAT.
Conflicts of interest and independent surveys
The DfE treats conflicts seriously: "A conflict of interest could lead to your application being disqualified, your final score being reduced, or your application being placed on hold whilst further due diligence is carried out." Schools should consider any conflicts the adviser may have with others in the application, "such as those undertaking the condition reports or tendering for the works". Tenderers must declare their interests, and the school must declare potential or perceived conflicts in the application form.
The condition evidence has its own test. "The survey source will not be considered independent if, for example, it is conducted by a firm that has also quoted or tendered for the work or is a manufacturer of any proposed solution." Surveys should not be older than 1 October 2023. Where a school does not include the full survey, it must include the front page(s) clearly showing the name and qualification of the surveyor and the date.
A school planning new school condition surveys should settle who carries them out with independence in mind from the start. Special schools raise their own questions about what a condition survey should record, covered in the practice's article on condition surveys for special schools.
What does the DfE say about fees for CIF bid support?
The DfE does not set a fee for CIF bid support; it sets a test: "Fees must be proportionate to the type of project being delivered." On percentage fees, it says "Percentage fees are not necessarily appropriate for this type of work and if used, they should be a maximum of 10% of the total project value." That ceiling "includes all professional fees and disbursements, as well as one off ‘bid writer’ fees, not just the technical adviser fee."
There is some room for harder projects. The DfE says "The technical complexity of some works may justify slightly higher fees (but not necessarily above 10%)", and "the higher fee level must be specifically justified within the application." It adds: "Please be aware that 10% is not a default fee allowed for the CIF programme." Schools "should not assume that fees below 10%, or any ‘no-win-no-fee’ arrangements automatically offer good value for money", and "If the fees are disproportionate to the work involved, your application is likely to be unsuccessful."
Advisers' costs can be funded: "If you are successful, we do cover the costs of appointing a technical adviser to help prepare your application and for oversight and management of CIF projects." The money is tied to that role, though. "You cannot use technical adviser fees, identified within the bid, to undertake additional works if you then manage the project in-house."
Page limits, project need and project planning
The scoring weights and page limits are summarised in the key dates and rule changes guide. For an adviser preparing the uploads, two formatting rules matter. Supporting documentation for project need, project planning and project cost is limited to 50 pages per document, "formatted in Arial font, no smaller than size 11." Anything submitted "beyond the 50-page limit for a document will not be considered as part of the assessment."
Project need carries the most weight: "Project need accounts for 55 points from a total of 100 for condition projects". The narrative goes in the portal form, while the upload holds the evidence. That evidence is led by an independent, suitably qualified condition survey with condition grades and priority ratings, plus specialist reports where the issue needs them.
Project planning is scored separately: "Project planning accounts for 20 points from a total of 100 for all projects". Its sub-criteria are appropriateness of solution, timescales and delivery plan. The school must check with the local planning authority whether planning permission is needed before applying. An academy with a CIF project that impacts on school land "is likely to require a separate consent of the Secretary of State via a land transaction application". CIF approval does not provide that consent, and the approved project cannot proceed until it is obtained.
The costed options appraisal, project cost and feasibility
The costed options appraisal must show alternatives considered, "including the costs, benefits, and risks associated with each option." The guidance asks applicants to show lower-cost options were considered and to "Always present a “do nothing” option". Reusing one appraisal across bids is a serious mistake: "Applications may be disqualified where it is identified that the same costed options appraisal has been used in more than one application."
Cost is scored separately. "Project cost accounts for 25 points from a total of 100 for all projects and consists of four sub-criteria: overall costs, cost certainty, funding sources and environmental sustainability." Successful applications are funded on the cost section of the portal form, not the uploaded documents, so the two must agree.
Feasibility work depends on complexity rather than size. "You should carry out a feasibility study where your project may be considered complex with multiple options, regardless of value." The DfE's list of what a feasibility study should cover includes the design solution and why it will work, a detailed and robust cost management plan or a contractor's cost estimate, site issues and a risk register.
What support can a school get with a CIF bid?
Condition Improvement Fund support can cover the whole bid, from appointment and evidence through design, costs and delivery planning, and good support is measured against the guidance. Support worth buying for this round covers the following.
The adviser is formally appointed before any work starts, procured in line with the Academy Trust Handbook (or College Financial Handbook, where relevant), your procurement policy and DfE requirements, and scoped from bid through to delivery.
Conflicts are declared, and condition evidence comes from an independent source: not a firm that has quoted or tendered for the work, or a manufacturer of any proposed solution.
The evidence of need is specific to your buildings, not a narrative padded with generic statements.
The costed options appraisal is written for your project, with a do nothing option and lower-cost alternatives.
The design and feasibility study is in proportion to the project, with drawings where they show where the works sit.
The cost plan matches the portal form, with fees proportionate to the project and any higher fee level specifically justified.
The delivery plan is realistic for the project size, and the risk register lists specific risks for your project, not generic ones.
The planning position is confirmed and any land consents are identified early.
The accounting officer has enough time to read everything, sign the declaration and submit.
Related guides
CIF 2027 to 2028: key dates, rule changes and what to prepare by 15 December
CIF guidance for 2027 to 2028: where the official documents are and what each one covers
Choosing a CIF consultant as a standalone academy or small MAT: what track record actually means
Architects for schools: how to choose one for a capital project
Working on 2027 to 2028 bids with Grayling Thomas Architects
Grayling Thomas Architects is a RIBA Chartered Practice with over 20 years' experience that has designed and delivered multi-million-pound school buildings. On CIF projects we work as lead consultant and architect, preparing the evidence, design and costed options with the school, so the accounting officer submits a bid they understand and own. We are not a stand-alone bid-writing service.
We were CIF bid writer, lead consultant and architect for Dorothy Goodman School in Hinckley, a new building for an existing special school, funded through the Condition Improvement Fund. The DfE's Condition Improvement Fund guidance confirms applications are now open for 2027 to 2028. Any adviser appointment must follow your own procurement process, so starting early helps.
Our Condition Improvement Fund bid support page explains how we work. To talk about a project, use our CIF enquiry form.