Building work on a live school site: phasing, safeguarding and keeping teaching going

A single blue construction safety helmet resting on a plain white background

By Grayling Thomas Architects ยท November 2026


Building work during term time is possible when the site is split in two. The contractor gets a fenced, separately accessed compound, the school keeps safe and unbroken routes for pupils, and the noisiest, most disruptive tasks move into holidays, weekends or agreed quiet windows. The head's job is to decide early what must happen in the summer, what can run in term, and where classes go in the meantime. The contractor's construction phase plan then has to show, in writing, how those decisions will be kept.


This article is written for the headteacher or deputy who will be running the school while the work happens, and it covers the operational decisions rather than the funding or the design.


Should building work happen in the summer holidays or during term time?


For small works that fit inside the holiday, the summer is usually the right answer, and most heads would put everything there if they could. An empty site removes the hardest problems at once, because there are no pupils crossing the site, no noise in lessons and no safeguarding questions about contractors near children. Grayling Thomas Architects plans single classrooms, toilet blocks, secure lobbies and similar small works and modular buildings around the calendar for exactly this reason, "planning and scheduling these projects during school holiday periods" so that teaching is not interrupted.


Once the work is larger, the summer stops being enough. A new teaching block, a hall or a substantial extension will take longer than one holiday, and squeezing it in tends to cause the outcome every head fears: a building that is not ready in September, with no plan for where the classes go.


A more useful question than "summer or term?" is which tasks belong in which period. As a rule of thumb, the holidays should take anything inside occupied buildings, work to the services that teaching relies on (heating, power, water, fire alarm), connections between old and new buildings, demolition near occupied rooms, and the final move into new spaces. Term time suits work inside a fully separated compound, such as foundations, frame, roof and envelope, along with fit-out of a building pupils do not yet use. Weekends and after-hours slots are for large deliveries, crane lifts, noisy cutting and anything that briefly needs the shared entrance. Set the timetable up this way and the term-time part of the job becomes a matter of separation rather than tolerance.


Phasing a project around a working school


Phasing is how a large project stays compatible with a school that never closes, with each phase handing back something usable before the next one starts. The clearest example from the practice's own work is All Saints Primary School, where the challenge was "to design a building occupying as little ground area as possible, enabling the existing junior school to operate fully during the new build, only two meters away".


The construction was split into three phases: "Enabling works and MUGA; School hall as two temporary classrooms; New 420-place primary school." The second phase delivered the school hall, which was used as two temporary classrooms while the main building went up, and "The existing school was eventually demolished to complete the landscaping." The lesson for a head is that phasing is decided at design stage, not by the contractor once on site. The order in which spaces are built, and which of them can serve as temporary accommodation, has to be designed in from the start.


Separating the site from the school


The single most useful thing a head can insist on is a physical line between the construction site and the school, held for the whole job. That line should be agreed on a site plan before work starts. Around everything the contractor controls, including storage and welfare cabins, the compound boundary needs a full-height fence rather than tape or barriers. The contractor should have a separate entrance, and if the site has only one gate, decide who uses it when and put a banksman on every vehicle movement.


Delivery windows belong in the contract, keeping lorries out of the drop-off and pick-up periods, playtimes and lunch. The plan should also mark how classes reach the hall, dining room, playground and toilets when part of the site is closed, and those pupil routes are worth walking with the staff who use them. Check that every fire evacuation route and assembly point still works with the compound in place. Finally, agree the handover line: how and when any area passes from the contractor back to the school.


The DfE's health and safety advice for schools says they "should also have procedures for controlling access and barring individuals from school premises." A construction project creates a second set of people with access to the site, and the plan should make clear how the two sets are kept apart.


Safeguarding and contractors on the school site


Contractors who stay inside a separated compound rarely meet pupils. The safeguarding risk is concentrated where the two worlds overlap, which means work inside the school, shared entrances, toilets and the end of the day when gates open.


In line with your own safeguarding policy, decide what checks you need for anyone who will work where pupils are, and put that requirement in the contract before the contractor prices the job. The practical rules are then agreed with the site manager. They should settle how operatives sign in and are identified, whether by badges, hi-vis colours or a register held by the school office, and confirm that nobody works unsupervised in occupied areas and who escorts them. Contractors should use their own welfare facilities rather than pupil toilets, there should be rules on phones, photography and smoking at the boundary fence, and the site manager needs to know who to call if a pupil is found on the wrong side of the line.


The DfE's health and safety advice lists contractors alongside staff, pupils and visitors among the people whose health and safety a school's risk assessments must consider. Update yours when the work starts, and again at each change of phase. The same guidance says to review the assessment if "there has been a significant change in related matters", and a building site arriving next to classrooms is one.


Exams, noise and the school calendar


Before the contractor programmes the job, give them your calendar for the whole contract period, covering exam weeks, mock exams, assessment weeks, open evenings, performances and sports days. Ask for a programme that shows how noisy work avoids them, and for a named quiet-working rule (for example, no breaking or cutting during timed papers) that the site manager can enforce without referring back. For a science block, where exam groups need working labs in every phase, our guide to refurbishing a school science block covers how to plan the phases.


Noise also depends on what is next to what, so a hall used for exams should not sit beside the compound if another room can be used. For pupils with SEN, sudden noise, vibration and changes of route can matter more than they do for others. Plan visual timetables, social stories and quiet spaces with the SENCO before the hoarding goes up.


Decant classrooms and temporary accommodation


Where a class has to move out of its room, there are three usual options: a temporary modular classroom, a room elsewhere on site (often the hall or library), or a finished part of the project used early, as at All Saints. The choice depends on cost, how long the move lasts, and how much of the school's daily routine it disrupts.


Temporary classrooms need their own planning, with a base, power, data and a safe covered route, all sited somewhere outside the construction compound. The practice's article on CIF funding for modular and temporary classrooms sets out what a Condition Improvement Fund bid can and cannot cover for decant space.


Tight timescales are workable when the end date is fixed and everyone plans to it. At Mendlesham SEN, the practice worked on the conversion of a community hall into "2 SEN Specialist Classrooms, Group Rooms, Offices and Toilets". The project "was limited to a tight timeframe to enable students to move in to the building at the start of term", and "was constructed in 16 weeks." The start of term was the date that mattered, and the programme was built backwards from it.


How do schools keep teaching safely while building work happens on site?


Schools keep teaching safely by treating the project as a change to how the school runs, not just a building job. In practice that means a separated site, a phasing plan agreed at design stage, updated risk assessments, clear safeguarding rules for contractors, and a programme that respects the school calendar. Responsibility is shared but not blurred. The DfE's advice says "The employer or, in the case of independent schools, the proprietor, is accountable for the health and safety of school staff and pupils", while the day-to-day running "is usually delegated to the headteacher and the school management team."


The legal framework for the building work itself is the Construction (Design and Management) Regulations 2015, under which the organisation commissioning the work is the client. HSE guidance says commercial clients must "ensure that the principal contractor or contractor (for single contractor projects) prepares a construction phase plan before that phase begins". Larger jobs are notifiable to HSE where work "will last longer than 30 working days and involves more than 20 workers at any one time; or where the work exceeds 500 individual worker days". The HSE's guidance for commercial clients sets out the full list of client duties, and our guide to a school's CDM 2015 duties as client explains each one in turn, from pre-construction information to the health and safety file.


What should a construction phase plan cover for a school?


A construction phase plan for a school should cover the site's own boundaries, routes, rules and timetable, not generic arrangements. It is the contractor's document, but it is the head's best tool for holding the job to account. Ask to see a draft before work starts and check that it covers each of these points specifically for your site:


  • It shows the compound boundary and how it changes at each phase.

  • It sets out vehicle routes, delivery times and banksman arrangements.

  • It marks pupil and staff routes, including fire escape routes and assembly points.

  • It states the sign-in, identification and supervision rules for operatives.

  • It gives the working hours, quiet periods and the exam and events calendar.

  • It explains how work inside occupied buildings will be closed off.

  • It says how dust, noise and services shutdowns will be managed and notified.

  • It names a site manager and a school contact, with a weekly meeting.


If the plan reads like a generic template, send it back. A plan that does not mention the school's own routes and timetable will not protect them.


Keeping parents informed


Parents notice building work before anything else: the fence, the lorries, the changed drop-off. Tell them before the compound goes up, with a simple site plan, the new walking routes and the delivery times. Repeat the message at each phase change and say clearly what will be different for their child, such as a class moving rooms. A short update in the newsletter, with a photograph of progress, does more for goodwill than a long letter at the start.


Related guides



Building work on live school sites at Grayling Thomas Architects


Grayling Thomas Architects is a RIBA Chartered Practice that designs and delivers school buildings. We plan phasing, site separation and temporary accommodation into the design, so that the school can keep running while the work happens, and we take projects from first brief to completion on site through our design and construction service. Our wider education and SEN architecture work covers new buildings, extensions and refurbishments for schools.


If your school is planning work and you want to talk through how to keep teaching going, contact Grayling Thomas Architects.

Get in Touch

Oxford

โ€‹

7 Goddards Lane

The Theatre Chipping Norton

Chipping Norton

OX7 5NP

โ€‹โ€‹

โ€‹

โ€‹

โ€‹โ€‹

โ€‹

โ€‹

03300 576 563

  • LinkedIn
  • Instagram

Thanks for submitting!

Get In Contact With Us

Thank you for reaching out to Grayling Thomas Architects. Your inquiry is important to us, and a member of our team will get back to you shortly to assist with your needs.

bottom of page